08 Oct Antwerp Dry-Bulk Project : Construction Progressing as Planned
Antwerp Dry-Bulk Project : Construction Progressing as Planned
Since our May update, the transformation of Euroports’ dry-bulk operations in Antwerp has continued to progress according to plan.
The demolition of the old warehouses is now complete, while groundworks and the construction of the new warehouse floor and walls have advanced significantly. The upper structure and roof are currently being installed, marking another important milestone in the project.
The first two warehouse boxes are expected to be commissioned by the end of October, with the full warehouse scheduled for completion at the beginning of Q1 2027.
This major investment will deliver more than 32,000 m² of new dry-bulk storage capacity, alongside upgraded infrastructure and on-site renewable energy generation, this warehouse will likely become the largest in Antwerp.
We look forward to seeing this new facility take shape and to continuing to support our customers with modern, efficient and future-ready dry-bulk solutions in the Port of Antwerp-Bruges.
